CEFCAC Procedure
- Project Nomination
Each year the cities are invited to
present their needs and priorities to CEFCAC for consideration. County
divisions are also invited to nominate projects.
Nominating agencies
are requested to provide their submittal by around middle October
using the Project Nomination Form. A separate request must be submitted
for each project. The request should include as much of the following
information as is available.
- Facility name. Limits of requested project.
- Facility number.
- City priority.
- History of flooding including property damage or potential for property
damage. Specific examples and dates are requested.
- Description of existing facility including flow capacity. Include
ownership and maintenance responsibility for existing facility.
- Description of drainage area including land use and size in acres.
Include map showing tributary drainage area, project location and
description. Also, attach adopted Master Plan of Drainage.
- Proposed project description by reach.
- length
- design flow rate
- recommended section
- number of crossings
- right-of-way requirements
- estimate cost
- Funding considerations:
- Offer to participate in joint funding.
- Developer participation (Section VII, Tentative Tract Conditions of
Approval).
- Redevelopment agency participation. Is project in a redevelopment
area?
- Conformance Report for locally owned facility. Requests for locally-owned
projects must include a Conformance Report or they will not be
considered for OCFCD funding.
- Additional information as applicable.
- Environmental documentation
- Project report
- Service agencies
- Utility relocations
- Right-of-way information
- Dates of prior request for this project
- Construction phasing
- Project readiness
The Project Request Statement should be addressed
to:
Manager, Flood Control Division
OC Public Works (OC Public Works)
P.O. Box 4048
Santa Ana , CA 92702-4048
- Project Review and Program Adoption
OC Public Works/Flood Control Division staff
field reviews each nominated project, reviews the project scope, need,
funding considerations, and cost and prepares a Project Summary Report
for presentation to CEFCAC.
Based on this information, the committee
prepares a prioritized list of projects for preliminary engineering (project
report), right-of-way acquisition, final design and construction. This
list, along with the District’s
operational requirements, is used to formulate the annual budget request
for County Administrative Office review and Board of Supervisors public
hearings.
The project is finalized upon adoption of the District budget
by the Board of Supervisors.
- Administration
- Plans and specifications for OCFCD projects will be prepared by OC Public Works
staff and by engineering firms in private practice. Work performed
by private engineers will be under the control and direction of the
Director of OC Public Works, OC Public Works. Work within
city limits requires approval of city council prior to award of contract.
- OCFCD projects will, in general, be constructed by private contractors
through contracts awarded by OC Public Works on the basis of competitive bidding.
- Locally-owned projects will, in general, be constructed in cooperation
with or by other agencies under agreements with the Flood Control
District or County of Orange.
|
 |
|