Introduction
History
Project Description
Lower Santa Ana River
Seven Oaks Dam
Prado Dam
Local Cooperation Agreement
Project Cost and Schedule

Project Cost and Schedule

Projects Year Began Estimated
Year Complete
Total Cost
Lower Santa Ana River 1991 2006 367 Million
Seven Oaks Dam 1994 1999 464 Million
Prado Dam 2003 2010 420 Million

In 1989, the Corps of Engineers estimated the costs of the Santa Ana River Project for each feature.

Project Cost in Millions chart

According to the Corps of Engineers, the Federal government will pay for about 2/3 of the total project cost; the local sponsors will be about 1/3.

Project Cost Share chart

The Corps of Engineers provides an estimate of the cost-share among the local sponsors based on the Corps estimate of the benefits of the Feature to each sponsor. These estimates shown on the above chart indicate that Orange County Flood Control District will pay 92% of the local sponsor's share of the Project.



 