Project Cost and Schedule
| Lower Santa Ana River |
1991 |
2006 |
367 Million |
| Seven Oaks Dam |
1994 |
1999 |
464 Million |
| Prado Dam |
2003 |
2010 |
420 Million |
|
In 1989, the Corps of Engineers estimated the costs of the Santa Ana River
Project for each feature.

According to the Corps of Engineers, the Federal government will
pay for about 2/3 of the total project cost; the local sponsors will be about
1/3.

The Corps of Engineers provides an estimate of the cost-share
among the local sponsors based on the Corps estimate of the benefits of the
Feature to each sponsor. These estimates shown on the above chart indicate
that Orange County Flood Control District will pay 92% of the local sponsor's
share of the Project.
|