Completed NFC Projects - Huntington Beach Channel (Indianapolis
Ave. to Adams Ave.) Phase 2
Huntington Beach Channel (Indianapolis Ave. to Adams Ave.) Phase 2
OCFCD Facility No. D01
Indianapolis Ave. to Adams Ave.
Located in Huntington Beach
Supervisorial District 2
Project Information
The construction project is the last segment of flood control improvements needed
to provide 100-year flood protection for residences and businesses in the area of
Huntington Beach from Indianapolis Avenue to Adams Avenue.
The work to be done, in general, consists of the following: clearing and grubbing;
excavation and transportation of saturated and unsaturated earthen materials; channel
grading and minor fill; placement of riprap material; removal and installation of
gates and fencing; placement of concrete and asphalt paving; construction of drainage
ditches, PVC drains, concrete drives, and installation of flapgates; removal of
brick and mortar plugs; coordination with utility companies, district personnel,
regulatory agencies, City staff, and adjacent property owners.
The remaining work, primarily the removal of the soil material from within the channel,
will allow the channel to convey 100-year storm discharges. The completion of improvements
in this last segment of the Talbert Valley flood control improvements will enable
RDMD to submit a request to the Federal Emergency Management Agency (FEMA) to remove
the flood plain designation from the area, thereby eliminating the requirement for
flood insurance.
The subject project has been budgeted for construction as part of the Fiscal Year
2006-2007 Flood Control Program.
The following is a link to the Notice to Contractors Section, Special Provisions
and Construction Plans. (Click Here)
Click
map to view PDF
|
|
|
|
|
|
Project Contact:
Penny Lew
714.834.2606
|
|
|
|
|
|
Start Date: 5/2007
|
|
|
Est Completion Date: 11/2007
|
|
|